Dry Dock 5 Construction Progress: July 2026

JOINT BASE PEARL HARBOR-HICKAM, Hawaii — Officer in Charge of Construction Pearl Harbor Naval Shipyard (OICC PHNSY) continues to lead the Navy’s largest military construction project.

Recent progress includes the installation of the north cofferdam and the welding of 12 upper and lower segments of 85-inch-diameter piles driven 150 feet deep. Crews also drove 72 pump-well tension piles to a tip elevation 210 feet below the water’s surface.

During nighttime diving operations, crews placed 1,385 cubic yards of tremie concrete 40 to 60 feet underwater, completing the perimeter connection among Prefabricated Floor Unit 2, Kahoʻolawe and the dry dock shoring wall.

To support crane rail and building foundations, crews drove 41 precast, prestressed concrete piles as deep as 135 feet and placed more than 350 cubic yards of concrete for crane rail grade beams.

Preparations to remove water from the dry dock are also underway, with all associated piping and temporary water-containment tanks installed.

Legal Disclaimer:

EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.

Share this page:

Advanced Search Options

Search for:

Search scope:

Type:

Search in:

Date range:

The last

Sort by:

Sign up for:

Construction Press Releases

The daily local news briefing you can trust. Every day. Subscribe now.

By signing up, you agree to our Terms & Conditions.